Project Information

Output: 500kW

Turbine Arrangement: 1 X Turgo supplied by Gilkes

Gross Head: 88m

Design Flow: 748 litres/second

Penstock Length: 2.2km

Location: Glen Moriston

Commissioned: Nov 201

Private HV System: 6.5km of underground cabling installed with a cable plough