Allt Garbh

Project Information
Output: 1.5MW
Turbine Arrangement: 1 X vertical multi jet pelton supplied by Kössler
Gross Head: 146m
Design Flow: 1320 litres/second
Penstock Length: 2.55km
Location: Glen Affric
Commissioned: Jul 2017
Private HV System: 9km of trenched cabling linking two projects (3.5MW total) to the National Grid